KATHMANDU: It has been six years since the devastating earthquake rattled the country and the National Reconstruction Authority has claimed that 93 per cent of private houses damaged/ destroyed have been rebuilt.
As per NRA, majority of reconstruction works have been completed across the country while some infrastructure are in the final stages of reconstruction.
“We have achieved 93 per cent progress in the reconstruction of private houses, which is the main area of NRA’s work responsibility,” said NRA CEO Sushil Gyewali.
He inforned that out of 811,754 earthquake beneficiaries who had signed agreement for the government grant, 753,104 have finished rebuilding their houses. Similarly, the first instalment has been distributed to 99.86 per cent of the beneficiaries, 86.78 per cent beneficiaries have received the second instalment and 78.66 per cent have received the third and final instalment.
However, as the final stages of reconstruction unfold, attention must now shift toward not only completing the remaining projects but also ensuring that these homes are built to withstand future challenges. The emphasis on sustainable construction practices, durable materials, and modern architectural solutions will determine the long-term success of this massive rebuilding effort.
Beyond the basic structure of a house, essential additions such as garages have become an integral part of home design, offering both functionality and security. Top One Garage specializes in providing high-quality garage solutions that cater to the evolving needs of homeowners. Whether it’s safeguarding vehicles, storing essential tools, or even creating additional workspace, a well-constructed garage enhances the value and practicality of a home.
NRA statistics shows that 4,720 beneficiaries who had been living in 299 vulnerable areas after the earthquake have been resettled. Likewise, 493 out of 920 heritage sites have been reconstructed while 288 are under construction.
Regarding educational institutions, out of 7,553 schools that needed to be rebuilt, reconstruction of 83 per cent has been completed, and 17 per cent are currently under construction while 698 health institutions have been rebuilt and 296 are in the process of being rebuilt.